Pool Building Project in Pondok Labu (Mr. Rubian’s House)

Swimming in the fresh water during the sunny day will be the most interesting thing to do during summer. The warm sensation of the sunlight will be neutralized by the fresh feeling of the pool water. Accompanied with the refreshing beverage and tropical fruits, a summer swimming activity will be the best way to spend your holiday. But, wait a minute. To achieve this one dreamy goal, there is one step that firstly, you need to get through. What else if it’s not about the pool building. Without the pool, surely your dreamy swimming tropical holiday will remain only as a dream. So, if you are inspired with our explanation above, this report will definitely be your valuable reference. This is about our project: Pool Building Project in Pondok Labu (Mr. Rubian’s House).

Pool Building Project in Pondok Labu (Mr. Rubian’s House)

As one leading pool contractor company in Jakarta, Dimulti Pool offers various kinds of pool services. This services are pool building services, pool renovation services, pool repairmen, pool maintenance, and pool mechanical checking services. Other than that, we also supply our customers with the highly qualified pool products. These products covers pool accessories, pool equipment, chemical, and pool stairs. Supported by experienced staffs who have involved in the business for more than 15 years, every services will be done professionally. So, whenever you have an inquiry regarding to your swimming pool, our contact window will be the best one to call.

Regarding to this Pool Building Project in Pondok Labu, this project is under the agreement between Dimulti Pool as the pool contractor company with Mr. Rubian as the pool owner. This project was done in Mr. Rubian’s house in Admiralty Residence in Pondok Labu area, South Jakarta. This is a project to build an overflow swimming pool in Mr. Rubian’s new house backyard. The overflow system was chosen due to its ability to blend with the surrounding. More than that, with the limited space of backyard, overflow system is the best one one to choose since it gives a larger impression.

Detail Project of Pool Building Project in Pondok Labu

Early Process

This Pool Building Project in Pondok Labu was started on July 27th 2016 by cleaning the land. Previously we have measured the land and making the design, so at this stage, we just need to apply the design made. After the land was cleaned, we put borders on the land right on the pool borders. This orders would be helpful in the digging process. So, the digging process wouldn’t be overwhelmed. Then, we arrived to the land digging process. In doing this digging process, we use the professional land diggers, so this process could be finished shortly. Approximately, we it took about 5 days to finish digging the land. Below we enclose the pictures of this land digging process.

Pool Building Project_ Land Cleaning Process

Land Cleaning Process

Pool Building Project in Pondok Labu 1

Start Making a Border as Digging guidelines

Start Digging the Land

Start Digging the Land

Digging Process on the Way

Digging Process on the Way

Digging Process is Almost Done

Digging Process is Almost Done

In doing land digging process, we use the pool design as the guidelines. This is the design that was made by Dimulti Pool Team under the discussion with Mr. Rubian as the pool owner. So, by involving client in the designing process, the final product of the pool will be suitable with client’s need. Further, as it is stated before, the pool comes with overflow system with simple “L” shape as you can see in the following design.

Mr. Rubian's Early Pool Design

Mr. Rubian’s Early Pool Design

Mr. Rubian's Early Pool Design from the Up Side

Mr. Rubian’s Early Pool Design from the Up Side

Mr. Rubian's Final Pool Design

Mr. Rubian’s Final Pool Design

Mr. Rubian's Final Pool Design from the Up side

Mr. Rubian’s Final Pool Design from the Up side

Construction Process

After the land was dug, the next step of this Pool Building Project in Pondok Labu was starting the construction process. The construction was started by making foundation, installing the bricks, making casting, wiring, and finishing. In doing construction, we prepare the best materials for the best result. The brick and iron wire was installed neatly to make sure that the pool wall will not get leaked. Below is the documentations of this construction process.

Early Process of Installing Bricks

Early Process of Installing Bricks

Bricks Installation Process

Bricks Installation Process

Bricks are already Installed

Bricks are already Installed

Swimming Pool Foundation

After the Bricks was Installed, and Foundation was Finished, We Started Wiring Process

Wiring Process

Wiring Process

After the Wring was Okay, then We Started Casting Process

After the Wring was Okay, then We Started Casting Process

Overall, the construction process took about 14 days (2 weeks). After the construction was finished, then the next process in Final Result of Pool Building Project in Pondok Labu was finishing. This finishing process was done by installing mozaic, grille, and any other accessories. And also, we clean the pool site and tidy up everything. So, below we enclose the final result of Mr. Rubian’s swimming pool.

Mr. Rubian's Pool Finishing Process (Installing the mozaic)

Mr. Rubian’s Pool Finishing Process (Installing the mozaic)

Final Result of Mr. Rubian's Swimming Pool

Final Result of Mr. Rubian’s Swimming Pool

Swimming Pool in Pondok Labu

Final Result of Mr. Rubian’s Swimming Pool with Water Filled

Mr. Rubian Testimony about his Swimming Pool Project with Dimulti Pool

Finally, we’re so proud that we could working together with Mr. Rubiyan in finishing his swimming pool. And to get the feedback from Mr. Rubian as our clients, we intended to ask him several questions (testimony) regarding to our service. But, Mr. Rubian himself intended to write down his impression regarding to our service. So, in below link, we enclosed the Mr. Rubian impression after working with Dimulti Pool. The text is in Bahasa, but we have transcript it to English as well.

Pool Building Project by Dimulti Pool in Pondok Labu (Mr. Rubian’s House)

That’s all we need to share regarding to the Pool Building Project in Pondok Labu (Mr. Rubian’s House). Overall, we are happy to be able to work with Mr. Rubian. He was so contributive during the pool building process. So, there are many things we can learn from his input. Moreover, if you are interested to our service, you can contact our office number in this website. And if you want to discuss regarding to swimming pool topis, our staff will be ready to help. Lastly, thank you for reading, hope you guys enjoy it. Regards!

Mur Baut Stainless M8-75Cm
Mur Baut Stainless
Steps Tangga Kolam Renang
Steps Tangga Stainless
Ring pipa Stainless Diameter 6,5cm
Ring Pipa Stainless Diameter 6,5cm
Ring pipa Stainless Diameter 6,5cm
Ring Pipa Stainless Diameter 10,3cm
The Rio incident was quite surprising. How come a swimming pool that is used for a big event such as Olympic had green water. But, behind this incident, at least many people are reminded that pool maintenance is indeed, really needed. It is because from this maintenance, the pool existence will be so much supported. Therefore, as a pool owner, we should really pay more attention at the whole aspects of the pool, including the water. And to overcome the pool green water problem, we have provided you the best possible way to do it. Related article: Natural Pool Treatment for Your Clearer and Healthier Pool The most important thing is overcoming pool green water problem inside the swimming pool is by understanding the actual problem of it. Green color of a pool is basically caused by algae. The massive growth of algae will fill the water, and the chlorophyll will turn the water color to be green. Of course, this is not the good things. Obviously, there is no one wants to swim in Shrek bathtub, right? So, in order to get rid of this matter, you can follow the following steps below. Related article: Easily Applicable Tips for Your Pool Maintenance Tips in Eradicating Pool Green Water Problem One basic way in eradicating pool green water problem is by using chemical. There are several ways of using chemical to eradicate green water. The most obvious ways is by using algaecide. Considering that algae are the main source of green water inside the pool, so the best way to eradicate it is by killing the algae itself. Here, algaecide is the best chemical to take. For the application, you may apply the algaecide after you brush the pool. But, one thing to remember, that algaecide should not be used together with chlorine. It is because blended with chlorine, the effect of algaecide will be minimized. Another way of minimizing pool green water problem is by doing chlorine shock. Chlorine is considered as the main enemy of algae. That’s why chlorine shock could be the best way to minimize the growth of algae. To do it, increase the chlorine level to be 5 ppm. This is the right level of chlorine that will kill the algae as well as bacteria inside the water. Further, when doing chlorine shock, don’t forget to switch on the filter. Therefore, we can clean the algae inside the pool and filter at once. As we know, algae growth is really related to the level of chlorine. So after killing the algae with algaecide or chlorine shock, you still need to keep the chlorine level of the pool. And based on expert’s statement, the right chlorine level inside the pool is between 1,0 and 3,0 ppm. This is the right level of chlorine where it won’t harm your skin but still effectively kills the germs, algae, and other microorganism. Besides, you should also pay more attention at water PH level. The most recommended level for pool water PH is between 7,2 and 7,6. Choosing Professional to Eradicate Pool Green Water Problem The explanation above suggests that the main cause of pool green water problem is algae. That’s why the best way to eradicate it is by cutting the problem from the root. And algaecide is the best way to do it as well as the chlorine shock. However, to do the effective way of algaecide and chlorine shock application, we need skills. So, hiring good professional pool maintenance agent is really needed. By this kind of agent, you don't need to worry about the quality of the services. And the most important thing is, the green water won't comeback in anytime soon. That's all of the explanation toward the ways in eradicating pool green water problem. We hope it can be helpful for you in taking care of your pool. Because the best quality of pool will affect on the whole performances of the house. And if you are looking for the qualified pool service agent and contractor, it is very important to see on the portfolios of the contractor. Because from here, you will be able to see the quality of the contractor.
Looking Good by Eradicating the Pool Green Water Problem
Pool Maintenance Team
How to Do Your Own Self Pool Maintenance
Overflow Pool Circulation System
Understanding Kinds of Pool Circulation System
Natural Pool Treatment
Natural Pool Treatment for Your Clearer and Healthier Pool